Construction coming along PDF Print E-mail
Written by Wauneta Breeze   
Friday, 14 January 2011 22:09

By Rebecca Strand

WP Journalism Staff

 

During Christmas break there was a lot of progress made on construction. The high school locker rooms are tiled, and now they are waiting to seal the tile and finish the showers.

The high school girls’ locker room has a white floor with red paint splatters and the boy’s is white with blue splatters. They are projecting the locker rooms to be finished by January 15.

The visiting locker rooms were used for the Hitchcock County game. The new ramp headed to the kitchen is open for use. That will make the lunchroom accessible for people with handicaps.

The new restrooms by the cafeteria are now functional and will be open when last minute clean ups can be made.

The lobby is still in work and the new concession stand should be finished around January 21.